Award-winning prefabricated CLT houses with timeless design

House foundations: what to consider for a CLT home?

The foundation for a factory-built house is the first concrete pour on the plot and the first place where such a house differs from one built on site: the elements do not give. If the foundation is two centimetres off or not level, the walls do not fit, and correcting that on site is expensive. That is why we talk about the house foundation so much before the first element goes into production.

Below are six things that decide which foundation a CLT house needs, what shapes its cost and how to write that line into your budget.

Why does the foundation of a CLT house need to be so precise?

CLT elements are manufactured in the factory according to detailed production drawings for each individual house. The walls, floors and other load-bearing elements arrive on site already cut to their final dimensions, with their positions defined to millimetre accuracy.

The same level of precision is therefore required from the foundation. The exact positions of the CLT elements are marked on the slab, and all necessary water and drainage pipes, floor drains, electrical feeds, conduits and other service penetrations must be positioned correctly before the concrete is poured.

These locations cannot simply be moved later. Even an error of a few centimetres can mean that a pipe or penetration ends up inside the wrong wall, outside the intended room or no longer aligns with the next stage of construction.

For this reason, a surveyor sets out the building and the relevant dimensions, axes, levels and project-defined positions are carefully checked. A precise foundation provides the correct starting point for CLT installation and for every construction stage that follows.

We look at technical service penetrations in more detail below.

TTUN9265
Norway house

What type of foundation do we use at Happy Home?

Our standard solution is an insulated reinforced-concrete slab foundation.

Its basic build-up is similar across our houses and, depending on the project, includes:

  • a prepared and compacted sub-base;
  • insulated plinth elements;
  • EPS insulation;
  • a reinforced concrete slab with the necessary local thickening;
  • perimeter insulation around the building;
  • project-specific service penetrations and technical preparations.

Special composite boards are also used beneath windows to help minimise thermal bridging.

The exact structural design of the foundation is calculated for the particular house and site conditions, while the underlying technical solution remains largely consistent across Happy Home projects.

Groundworks depend on the plot

Before the foundation is built, the topsoil is removed from the building area and the necessary excavation works are carried out.

Where suitable, the excavated topsoil can be left on the plot at the client’s request and later reused for landscaping or adjusting ground levels. If the plot is small, the volume of excavated material is large or the client simply prefers it, we can also arrange for the soil to be removed and disposed of as an additional service.

The area beneath the foundation is then filled and compacted using the materials specified in the design. A typical Happy Home quotation includes up to 50 cm of fill beneath the foundation.

If substantially deeper excavation is required to reach a suitable load-bearing layer, or if bedrock requires hydraulic breaking, additional works and material may be needed.

Situations that require a significantly different approach are relatively uncommon, but where necessary the solution and any associated cost are reviewed separately for the specific site.

Iceland house in Saku – an insulated foundation and a dry perimeter
Iceland house in Saku

Technical systems are already planned into the foundation

A foundation is not simply the structural base of the house. Before the concrete is poured, many of the services that pass through the floor or foundation must already be precisely defined.

Water and drainage pipes, floor drains, electrical and low-voltage conduits and other required penetrations are positioned according to the relevant technical drawings.

The building is provided with the required earthing system, and a temporary electrical distribution board is installed for the construction period.

For example, if the kitchen extractor is designed with an exhaust duct running through the floor, the duct is already installed at this stage from the kitchen location through the foundation to the exterior of the building.

These solutions therefore need to be resolved before the foundation is poured. This is one reason why the architectural, interior and technical designs need to be coordinated with one another early in the process.

When is radon protection needed?

Radon is a naturally occurring radioactive gas that originates in the ground and can enter buildings through structures in contact with the soil. It cannot be detected by smell or colour. Some areas of Estonia have a higher natural radon risk, particularly in Northern Estonia, although higher-risk zones also occur elsewhere.

A regional indication of radon risk can be checked on the Estonian Geological Survey’s radon risk map, while a site-specific survey provides more accurate information for an individual plot.

Radon protection is not installed automatically in every Happy Home foundation. The need for it is agreed with the client based on the site and the information available.

If a radon survey indicates an elevated risk, or if the client prefers to add protection as a precaution without commissioning a survey, a radon membrane can be installed between the insulation layers of the foundation.

Where the radon risk is higher, the design may also include additional measures such as radon sumps, extraction pipework or provision for a radon fan. These solutions are designed and priced separately according to the specific project.

Any necessary measures should ideally be agreed before the foundation is completed, as adding them later is considerably more difficult.

Norway house in Karikakra – the foundation and site works are done before the elements arrive
Norway house in Karikakra

How is rainwater managed?

Rainwater drainage is shown as a separate item in the Happy Home quotation and is installed for a large proportion of our houses.

The required rainwater gullies and pipework are installed around the house so that water collected from the roof is directed safely away from the building according to the solution designed for the particular site.

The final discharge point depends on the plot, local conditions and the project. Depending on the site, rainwater may be directed into a stormwater network, infiltrated on the property or collected in a separate rainwater tank.

Rainwater management should be considered together with the site levels, foundation and overall external works from the design stage onwards.

When is perimeter drainage needed?

Perimeter drainage is different from the rainwater drainage system.

On some projects, drainage is required because of the soil conditions, site levels, groundwater or another technical consideration. In other cases, the client may choose to add it as an additional precaution.

Its purpose is to collect excess water in the soil and direct it away from the foundation. A typical system uses a perforated drainage pipe surrounded by free-draining gravel and geotextile, with the pipework laid to the required fall so that water can flow to the intended discharge point.

The exact layers, pipe locations and discharge solution are always determined according to the specific plot.

If perimeter drainage is included, it makes sense to install it together with the foundation and other groundworks. Adding the same system later, once the house, terraces and landscaping are complete, is considerably more complicated.

Japan house in Otepää – a sloping plot required a stepped foundation
Japan house in Otepää

We do not compromise on foundation quality

The foundation is difficult to correct later, and its accuracy directly affects CLT installation and every stage that follows. For this reason, we use a carefully developed foundation solution and do not compromise on the quality of materials, workmanship or execution.

Some clients choose to commission the foundation from their own contractor or organise this part of the construction themselves. That is entirely possible, but in such cases we carry out a thorough inspection before CLT installation, checking the foundation dimensions, levels, element positions and service penetrations.

We have encountered cases where inaccuracies in foundations built by third parties become apparent during preparation for CLT installation or during the installation itself – for example, where the structural dimensions or service penetrations do not correspond with the project. Some issues may also only become visible during later construction stages.

A non-standard foundation solution is rarely required, but certain plots or projects may call for one. This may involve a different type of foundation, unusually extensive groundworks, difficult rock excavation or another technical solution. In these cases, we discuss the options with the client and price the additional work according to the project.

The foundation sets the level of precision for the entire CLT house

Most of the foundation disappears from view once the house is complete, but its quality has a direct impact on everything that is built above it.

For a CLT house, a good foundation means more than sufficient structural capacity. It must have the correct dimensions and levels, be accurately set out, properly insulated and contain all required service penetrations and connections in exactly the right locations.

That is why we treat the foundation as a complete technical solution rather than simply a concrete slab. When the foundation is properly designed and precisely built from the outset, the accuracy of the factory-made CLT structure can continue seamlessly on site.

Get in touch!

For 16 years we have helped people create the home of their dreams. We advise you at every step – from the first question to a home where it feels good to be.

TTUN4139

Your complete new-home solution from a single provider

We offer house design, handle all the paperwork from building permit to occupancy permit, and build turnkey houses. Every house is built to an individual design. Working with our architect, you decide the size, floor plan and finishing materials of your house. We take into account both the shape of your plot and the path of the sun, and we can combine details from different houses to find the solution that suits you best.

We can also build projects that already have a building permit.

icon11

Award-winning design

Functional houses with timeless design and plenty of space
icon3.svg

Energy class A

Heating, ventilation, heat retention
icon1.svg

50-year warranty

On the structure and 2 y. on workmanship
icon8.svg

Choose your size and budget

A floor plan tailored to your wishes and budget
icon6.svg

Built fast

A turnkey house completed in five months

Award-winning CLT element houses with timeless design

Award-winning Happy Home designs and builds designer houses from cross-laminated timber (CLT). We have long-standing experience and offer home solutions for even the most discerning clients.

Our award-winning CLT element houses, with their timeless design, are created by architects, engineers and construction experts working together. Happy Home houses blend naturally into their surroundings and are built to last, in both construction quality and architecture.

We want to inspire people to live more environmentally conscious lives. We build sustainable thinking into each project from the design phase, when the first key decisions about materials and energy efficiency are made.

Yes. To request a price list, send us an enquiry through the form on our website. For an initial overview, we’ll send you sample price lists for our houses, showing design and construction costs as well as possible additional work. We can prepare a quote tailored to your needs after an initial consultation.

Preparing the design usually takes 1–3 months, obtaining the building permit around 2–3 months, and construction about 22 weeks. Interior finishing may extend the construction time. The exact schedule depends on the project, the solutions chosen and how quickly the necessary decisions are made.

Yes. We design every house individually. Working with our architect, you can choose the size, layout and finishing materials of your house. We take into account the characteristics of your plot and the path of the sun, and we can combine solutions from different houses. The floor plans on our website are examples that we can use as a starting point when designing your home.

Yes. Houses under construction can be visited by prior arrangement. We can also meet at our office or hold an initial consultation by phone or video call. We recommend sending us an enquiry before your visit so we can arrange a suitable site and show you the solutions that interest you most.

Yes. We also build houses designed by others. Before construction begins, we review the existing design and adapt the necessary drawings and technical solutions to our construction details.

If you already have a plot, we can handle the design, the documents needed for the building permit application, and the construction. Our scope of work does not include landscaping or furniture. You don’t have to order all the work from us – you can choose which work to order from us and which to arrange yourself.

Over 100 completed projects

Over 100 happy families

If you have a question, would like our price list or want to come and see our houses, write to us or give us a call.

Liisa Nirgi
+372 53 040 040
info@happyhome.ee