Occupancy permit for a house: 6 steps of how it works for a new detached house in Estonia

The occupancy permit for a house is the step that is talked about least and that creates the most paperwork for the owner of a finished house if it has not been prepared during construction. The building permit allows building; the occupancy permit allows living. Without it the building is not officially complete, which means trouble with the insurer, the bank and a future sale.

This article walks through six steps of how the occupancy permit works for a new detached house in Estonia, which documents and measurements it requires, and what Happy Home does for a turnkey client. The legal basis is the Building Code, and the application is filed in the building register.

Occupancy permit or notice of use: which one you need

The rule is simple and mirrors the building permit rule. If the building needed a building permit, it needs an occupancy permit, also called a permit for use, before it is used. If a building notice was enough, a notice of use is filed on completion. A new detached house is practically always a building-permit building, so it needs an occupancy permit; the notice of use concerns outbuildings, a smaller sauna house, a shed or a carport.

The difference is in the procedure: for a notice of use the municipality has ten days to raise additional requirements, and if no answer comes, the building may be used. An occupancy permit is an administrative act the municipality issues after checking the documents and, where needed, inspecting the building, normally within 30 days. The building permit side is in our article on the building permit in Estonia.

Japan house in Otepää – the occupancy permit is issued after the documents are checked and the house inspected
Japan house in Otepää

Step 1: documents collected during construction

The basis of the occupancy permit application is the construction documentation, which cannot be created afterwards. The following documents must be created and kept during the build.

  • The site log, recording the works, the weather, the checks and the participants.
  • Covered-works certificates for work that cannot be seen later: foundation, insulation, waterproofing, pipework before it is covered.
  • Minutes of site meetings and approvals of changes, where the design was deviated from.
  • Declarations of conformity and performance for the materials and products.
  • As-built drawings, that is the design as the house was actually built.

Happy Home’s project manager and site manager keep the site log and prepare the certificates as they go, so the file exists at the moment of handover. The stages where these documents are created are in our article on house construction stages.

Step 2: measurements and audits before the application

Before the application, measurements and audits have to be made that prove the house is safe and matches the design. The electrical installation gets a conformity audit, without which the installation may not be taken into use. The ventilation system gets an air-flow measurement and adjustment, and documentation is prepared for the heating system. If the house has a chimney or a heating appliance, fire safety documents are needed.

In addition, the energy label is prepared, which for a new building is a mandatory part of the occupancy permit, and an as-built survey is ordered that records the actual location and dimensions of the house in the register. What the energy label shows is explained in our article on the energy class A house.

Step 3: filing the application in the building register

The occupancy permit application is filed electronically in the building register, which the owner enters with an ID card, Mobile-ID or Smart-ID. The construction documentation, as-built drawings, measurements, audits, energy label and as-built survey are attached. The builder or the project manager may file the application under the owner’s authorisation, but the owner signs it and pays the state fee.

The amount of the fee is set in the State Fees Act. Review the application with the project manager before filing: a missing document means a round of completion, and the procedure clock restarts.

Iceland house in Kiili – a completed home whose occupancy permit file is assembled during construction
Iceland house in Kiili

Step 4: the procedure and the inspection

The municipality checks whether the building matches the building permit and the design and whether the required documents exist. The deadline of the procedure is normally 30 days; if the application needs completing, the time counts from when the deficiencies are remedied. The municipality may inspect the site before granting the permit and, where needed, involves other authorities, for example the Rescue Board on fire safety questions.

The most common causes of delay are deviations from the design that were not approved, a missing electrical audit or ventilation measurement report, an unfiled energy label and an unpaid state fee. All four are preventable when the file is built up during construction and reviewed before filing.

Step 5: permit in hand: insurance, the bank and the registers

Once the occupancy permit is issued, the building is recorded in the building register as in use. That is the moment to arrange home insurance covering the finished building and to present the permit for use to the bank, if the house is loan collateral. The energy label stays in the register and is asked for at a sale.

Keep the occupancy permit file as well: it is the passport of the house, and an insurer, a buyer or a renovator will ask for it later. We hand the client the complete documentation at handover.

Step 6: outbuildings and later changes

The same logic applies to outbuildings. A sauna house, garage or carport built under a building notice needs a notice of use on completion; a larger garage built under a building permit needs an occupancy permit. The simplest is to file the outbuilding documents together with the house, if they were completed at the same time.

If you later want to extend the house, change the roof or add an outbuilding, the cycle starts again: building permit or building notice, construction, and occupancy permit or notice of use. The register must match reality, otherwise the same problems arise at a sale or with insurance that the first occupancy permit solved.

Denmark XL model – a completed factory-built house with its outbuildings
Denmark XL model

What Happy Home does at this step

This is part of our turnkey service. The project manager and site manager collect the documents during construction, order the measurements and audits, prepare the as-built drawings and assemble the application by handover; the client signs it as the owner and pays the state fee. Everything inside our price is on the construction info page.

For planning purposes, the building permit takes two to three months in practice and construction about 22 weeks, and the occupancy permit file is built up over that whole period rather than at the end.

Iceland house in Mändjala – a home on Saaremaa completed with its occupancy permit
Iceland house in Mändjala

Summary

The occupancy permit file is not paperwork that starts after completion but a by-product of the build, which is why turnkey construction is the calmer route for a first-time builder.

If you would like that whole file to be the builder’s concern, send us the plot documents through the contact page. We start with the plot and finish with the occupancy permit.

May I live in a new house without an occupancy permit?

A building erected under a building permit may be used after the occupancy permit has been issued. Living without it is a risk: the insurer may refuse a claim, the bank requires the permit for its collateral, and a buyer asks for it first. That is why we file the application right after completion.

How much is the state fee for an occupancy permit?

The fee is set in the State Fees Act and is paid when the application is filed in the building register. A notice of use is free of charge. The owner pays the fee.

Get in touch!

For 16 years we have helped people create the home of their dreams. We advise you at every step – from the first question to a home where it feels good to be.

TTUN4139

Your complete new-home solution from a single provider

We offer house design, handle all the paperwork from building permit to occupancy permit, and build turnkey houses. Every house is built to an individual design. Working with our architect, you decide the size, floor plan and finishing materials of your house. We take into account both the shape of your plot and the path of the sun, and we can combine details from different houses to find the solution that suits you best.

We can also build projects that already have a building permit.

icon11

Award-winning design

Functional houses with timeless design and plenty of space
icon3.svg

Energy class A

Heating, ventilation, heat retention
icon1.svg

50-year warranty

On the structure and 2 y. on workmanship
icon8.svg

Choose your size and budget

A floor plan tailored to your wishes and budget
icon6.svg

Built fast

A turnkey house completed in five months

Award-winning CLT element houses with timeless design

Award-winning Happy Home designs and builds designer houses from cross-laminated timber (CLT). We have long-standing experience and offer home solutions for even the most discerning clients.

Our award-winning CLT element houses, with their timeless design, are created by architects, engineers and construction experts working together. Happy Home houses blend naturally into their surroundings and are built to last, in both construction quality and architecture.

We want to inspire people to live more environmentally conscious lives. We build sustainable thinking into each project from the design phase, when the first key decisions about materials and energy efficiency are made.

Yes. To request a price list, send us an enquiry through the form on our website. For an initial overview, we’ll send you sample price lists for our houses, showing design and construction costs as well as possible additional work. We can prepare a quote tailored to your needs after an initial consultation.

Preparing the design usually takes 1–3 months, obtaining the building permit around 2–3 months, and construction about 22 weeks. Interior finishing may extend the construction time. The exact schedule depends on the project, the solutions chosen and how quickly the necessary decisions are made.

Yes. We design every house individually. Working with our architect, you can choose the size, layout and finishing materials of your house. We take into account the characteristics of your plot and the path of the sun, and we can combine solutions from different houses. The floor plans on our website are examples that we can use as a starting point when designing your home.

Yes. Houses under construction can be visited by prior arrangement. We can also meet at our office or hold an initial consultation by phone or video call. We recommend sending us an enquiry before your visit so we can arrange a suitable site and show you the solutions that interest you most.

Yes. We also build houses designed by others. Before construction begins, we review the existing design and adapt the necessary drawings and technical solutions to our construction details.

If you already have a plot, we can handle the design, the documents needed for the building permit application, and the construction. Our scope of work does not include landscaping or furniture. You don’t have to order all the work from us – you can choose which work to order from us and which to arrange yourself.

Over 100 completed projects

Over 100 happy families

If you have a question, would like our price list or want to come and see our houses, write to us or give us a call.

Liisa Nirgi
+372 53 040 040
info@happyhome.ee